The World's Largest Wind Turbine

Back to xpda.com
 
These pictures and comments were stolen from REpower's web site.
They deserve all credit, except for the mistakes, which I claim.

pDSC04847.jpg
The work on the foundation for the prototype of the REpower 5M turbine (5MW), in Brunsbüttel, Northern Germany has been completed. Due to its height of 183 metres and its weight of 1,100 tons (rotor and nacelle: approx: 380 tons) the wind turbine requires an extremely large foundation.
pDSC04848.jpg
The foundation includes 40 concrete piles, each measuring 24 metres in length. 1,300 cubic metres of concrete and 180 tons of steel have been used. Only a circular base plate with a diameter of around 23 metres will be visible.
pDSC04850.jpg
pDSC04852.jpg
nbrunsbuettel1.jpg
Aerial view of REpower 5M site Brunsbüttel.
nbrunsbuettel2.jpg
Aerial view of REpower 5M site Brunsbüttel.
mREpower_5M.jpg
All the installation work on the nacelle and hub is completed. The heart of the REpower 5M is now clad and is ready to be taken away. The components are shipped on a pontoon along the Kiel Canal from Kiel to the Brunsbüttel Port on the River Elbe.
k5M_01.jpg
k5M_02.jpg
k5M_03.jpg
k5M_04.jpg
k5M_05.jpg
k5M_06.jpg
k5M_07.jpg
k5M_08.jpg
The turbine's central components - the hub and nacelle - were loaded onto a pontoon at Howaldtswerke-Deutsche Werft AG (HDW) where the turbine was assembled. The voyage via the North & Baltic Sea Canal will last approximately nine hours.
k5M_09.jpg
k5M_10.jpg
The three longest rotor blades ever produced, each having a blade length of 61.5 m, will be transported overland in a wide load convoy to Brunsbüttel from the Danish rotor blade manufacturer LM Glasfiber A/S.
k5M_11.jpg
k5M_12.jpg
j160904.jpg
Delivery was taken of the third rotor blade. The turbine should be completed in around ten days, depending on the weather.
h5M2_01.jpg
h5M2_02.jpg
h5M2_03.jpg
September 17, 2004. By erecting the tower the go-ahead for constructing the world's largest wind energy turbine REpower 5M was given in Brunsbüttel, Schleswig-Holstein today. The tubular steel tower consists of five individual segments which are screwed on top of each other. Today segments 1 and 2 with a height of 13.5 and 16.5 metres were completed. The height of segments 3 and 4 is 16.5 and 27.5 metres. The longest tower segment with a length of 40 metres is the last section to be installed. Together with the height of the foundation of 3 metres and 3 further metres in the nacelle section a total hub height of 120 metres is reached.
h5M2_04.jpg
The tower tapers from 6 metres diameter at the height of the foundation to 5.5 m at the top. It weighs a total of 750 tons and consists of 1,100 screwed connecting elements. The construction is based on a ferro-concrete foundation which is borne by 40 concrete pillars extending into the ground to a depth of 24 metres. Of the approx. 1,300 square metres of concrete and approx. 180 tons of steel which were used in the installation, only a circular plate with a diameter of 23 metres is visible.
h5M2_05.jpg
h5M2_06.jpg
g5m3_01.jpg
Construction of the third segment completed.
g5m3_02.jpg
f5m_01.jpg
The fourth section of the tower was placed in position and bolted. Thus the steel construction currently reaches a height of 73.5 metres. To continue the assembly work, the crane will be lengthened today from a hook height of 105 metres to 135 metres. This will enable it to lift the fifth and final tower section, with a length of 40 metres, and the nacelle components and the rotor to a hub height of 120 metres.
f5m_02.jpg
e5M_01.jpg
e5M_02.jpg
The 136-metre-high crane (135-metre hook height) was extended so that work can begin on assembling the fifth and last part of the tower with a length of 40 metres. When this is completed, the nacelle will be installed in several stages.
e5M_03.jpg
d5m_01.jpg
d5m_02.jpg
d5m_03.jpg
Last part of tower errected and installation of nacelle started.
d5m_04.jpg
d5m_05.jpg
c5m_01.jpg
c5m_02.jpg
c5m_03.jpg
c5m_04.jpg
September 27, 2004. With the installation of the fifth and final tower section having been completed, the assembly team has now begun installing the 18-meter-long, six-meter-wide and six-meter-high nacelle on the tower. The nacelle is being assembled in several sections. First of all the lower part of the nacelle was installed on the tower yesterday with the motor support, part of the cladding and a large part of the cabling.
b5m_01.jpg
This was followed by the drive train - the mechanical core of the turbine - with a rotor shaft supported on two bearings, rotor locking brake and gearbox. In further stages the generator, transformer, deck crane and the upper part of the nacelle cladding will be assembled at a height of 120 meters.
b5m_02.jpg
b5m_03.jpg
b5m_04.jpg
Nacelle completed
a5m_01.jpg
The third and final phase of construction work to build the world's largest wind turbine, the REpower 5M, begins today with the fitting of the rotor. The rotor has a diameter of 126 meters and, when rotating, sweeps across an area of 12,469 square meters. This is roughly the size of two football pitches. Under normal operating conditions, the rotor will turn in relation to the wind speed at between 7 and 12 revolutions per minute.
a5m_02.jpg
a5m_03.jpg
First of all, the three rotor blades, 61.5 meters in length and weighing 18 tons each, will be fitted to the hub on the ground. In the next stage, the main crane will lift the rotor, with a total weight of around 120 tons. While it is being lifted, a secondary crane will guide the rotor from its horizontal starting position into a vertical position. At a height of 120 meters, the rotor will be fitted to the turbine. Here the hub will be fitted to the rotor flange of the power train.
5m_01.jpg
5m_02.jpg
5m_03.jpg
Following installation of the three 61.5-meter-long rotor blades at ground level, the crane then had to perform its most difficult hoist of the erection work. The rotor, with its diameter of 126 metres and total weight of 120 tonnes was lifted into a horizontal position and then brought into a vertical position by a follow-up crane. At a height of 120 metres, the hub was connected to the drive mechanism flange. With that, all the essential work on the prototype of the 5-megawatt turbine, the REpower 5M, was concluded after just nine days' net working hours.
5m_05.jpg
5m_06.jpg
5m_01.jpg
4 October 2004. With the installation of the rotor on Friday evening, all the essential assembly work on the REpower 5M had been successfully completed.

By the end of the year, the largest wind turbine in the world with a rated output of 5 megawatts and a rotor diameter of 126 metres, will be supplying the grid with enough power for around 4,500 average households.